Thanks for the clarification, Jonathan (and I've clicked your red house many times before ).

I went to the office today to check on the construction progress. Here's where we are as of today.

This is the view when one enters the waiting room. Once the tank is in place, cabinets will be built down to the floor and up to the ceiling around the entire perimeter of the system.


Here's the lockable door to the tank equipment room.


This is the stand. It's powder coated and strong as, well, you know.


This will give you a better idea of just how thick the metal is on this stand. That oughta hold'er.


Inside the equipment room is a janitor's floor drain with a water source/faucet above it (not pictured but partially seen in the first image).


The walls of the equipment room are painted with a gloss paint that will deter corrosion. To assist with temperature control, the equipment room has its own HVAC unit.


And finally, here's the view from the tank room, looking into the waiting room.
__________________
The Dude abides