Update

Sorry there's not been much to update recently. The basement contractor is starting in 11 days (T-11) so I'm still stuck in FULL PLANNING MODE.

So, all I have is more plans and ideas. It might be overkill but the planning is so much fun and I'd really like to get as much more input from everyone as I can, BEFORE I start building this monster.

So, as usual, any feedback...bring it on!



I'm going to post my latest detailed plans:

First, a pic of the part of the basement that will be my fishroom:



Now, a step by step visual of the build out process (this is uploaded to powerpoint so I can give my contractor an actual "Slideshow" when we have our pre-meeting next week).

Same shot as above, in grahpics mode:



Now, 2 walls will be added to make an 8x10 "Fishroom"



Next:
1) Cutout in wall for tank (I'm going to add some space above the tank for access in the front)

2) 3 dedicated lines (2 15Amp, 1 20amp) for the equipment

3) Hot and cold water lines to be run for the sink

4) PVC out for the pump in the sink

5) Exhaust tube to be run for climate and humidity control



Next, add:

1) Stand for tank

2) Sink

3) RODI system




Add the tank:



And finally, some sort of work table along with back - need to keep it narrow b/c I want as much space to work with as possible. Will probably keep my QT tank on here.



Thoughts? get 'em in now before its too late